Quantitative analysis: PERT

written by - Comments off

A project having the following six activities:

Activity Immediate Crash
Predecessors Time (weeks) Max Crash cost per week
A none 7 7 N/A
B none 3 2 $750
C A 5 3 $1,000
D A, B 6 4 $2,000
E C, D 4 3 $1,250
F D 3 2 $1,000

1. Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task

2. List the tasks on the critical path

3. What is the expected project duration in weeks?

4. What is the slack for each activity?
A: ________ B:_______ C:________ D:_______ E:_______ F:_______

Note: Currently, Regular Priority times are 3-5 days. Log in to upload files with your questions. Tutorials you buy shall be emailed to your PAYPAL email. Talking about quality references: finding and referencing an (n+1)th article for your tutorial requires substantially more time than the (n)th article referenced, therefore you will see the price increasing with the number of references you require in some questions. Wanted to contact us over something related to this question? Email us: support AT oxenmine.com.